MDOT to hold meeting on 2020-21 M-28 project in Munising

Photo courtesy: Michigan Department of Transportation; Munising Map

MUNISING, Mich. (WLUC) - The Michigan Department of Transportation (MDOT) invites the public to a meeting to discuss the 2020-21 M-28 reconstruction and roundabout project in Munising, which also will include a shared-use pathway, city utility work, and streetscape improvements.

There will be a short presentation followed by a question-and-answer period on Tuesday, July 23, at 4 p.m. It will be held at American Legion Post 131 at 610 West Munising Ave. in Munising.

There will be opportunities for residents and business owners to ask questions or speak one-on-one with MDOT, design consultants, and city officials.

Attendees will also have an opportunity to take an online opinion survey on elements of the streetscape design.

The presentation portion of the meeting will be available on Twitter at www.twitter.com/MDOT_UP.

BACKGROUND
Beginning in 2020, MDOT will reconstruct M-28 between Brook Street and Commercial Street in Munising and resurface the highway from Commercial Street to east of Christmas.

The shared-use pathway will be constructed along the north side of M-28 from Bayview Drive to the intersection of M-28 and Alger County Road H-58.

A roundabout will be constructed at the M-28/H-58 intersection.

The project is expected to be completed in 2021. The budget for the road work is estimated at $13.5 million.



 